| The guys are working on framing in the NW end of the roof. | 
|  | 
| The mini wall on the west side of the church is sheeted and ready for the next step. | 
|  | 
| Rafter hanger. | 
|  | 
| Putting sheeting on the NE corner of the roof. | 
|  | 
| Framing the NW section of roof. | 
|  | 
| Uh... yikes! | 
|  | 
| Leftover stuff from the month of September. (hunting season) | 
|  | 
| Fire hydrant in its place in the parking lot. | 
|  | 
| Excavators hooking the main water line up to the church. | 
|  | 
| Framing. (notice the green grass) I'm pretty sure that's unusual this time of year. | 
|  | 
| Getting instruction on pulling nails. | 
|  | 
| Removing nails from the roof. | 
|  | 
| Trying to get the well pump up and running again for temporary water. | 
|  | 
| What's better then an audience when working? | 
|  | 
| Multitasker. | 
|  | 
| Looking into the church from the South side. | 
|  | 
| Soon to be sanctuary. | 
|  | 
| NE corner of the church. | 
|  | 
| Looking south from the very front of the church. | 
|  | 
| Framing is almost complete. | 
|  | 
| East side of the church. Lower roof framed and sheeted. All that's left is that upper roof on both sides. | 
|  | 
| With these early nights, lights are a must. | 
|  | 





























 